Shakunt Vilas: Minutes of the Meeting -24.06.2025
Date: 24-06-2025
Time: 9AM - 10AM
Attendees:
· Mr. Charith [Client]
. Mrs. Shantini [Client]
· Ar. Kiran Nayak (Principal Architect)
key points:
1. Owner–Contractor Agreement
To ensure clarity and avoid disputes during construction, we recommend the following clauses be added or clarified in the contract:
Design Revisions & Changes
Define the process for implementing design changes during construction.
Clearly state:
Who is authorized to make changes.
When changes can be discussed and approved (preferably during coordinated site or office meetings).
How the impact of changes on cost and timeline will be assessed and communicated.
Dispute Resolution & Termination
Include a clear clause outlining the process for dispute resolution and conditions for contract termination, if required.
Workmanship & Material Quality
Outline penalties and corrective procedures for poor or incorrect workmanship.
Specify:
Who reviews and approves brands/makes for key materials (steel, masonry, concrete, etc.).
The process for approving substitutions if any deviations are proposed.
Retention Clause
Include a retention amount (typically 5–10%) to be held until the end of the defect liability period. This ensures post-construction issues are addressed.
Cost Escalation
While basic rates are included, the contract should define:
How inflation-linked cost escalations will be handled.
The notice period required before clients are informed of rate changes.
2. Interior Design & Layout Coordination @Tall Storeys Projects
Material Preferences:
Marble flooring to be used throughout the flat as per C+S’s preference.
Room Configuration:
Arnav’s room will be located next to the master bedroom (near the lift).
The bar unit will be similar in size and scale to Dr. Ranga Nayak’s.
Layout Planning:
Begin work on detailed layout options that affect architectural elements:
Bathroom and kitchen configurations
Any proposed changes to room layouts
Time-Sensitive Coordination:
The location of the internal terrace stair and powder room must be finalized at the earliest.
This needs coordination with the Archemy team and integration into site drawings.
Kick-off Coordination Call:
Dr. Charit will arrange a virtual meeting with C+S, Tall Storeys, and Archemy to align on design intent and initiate architecture–interior coordination.